Santos happy as GLNG project remains on track for 2015

The GLNG project on Gladstone's Curtis Island is 45% complete.
The GLNG project on Gladstone's Curtis Island is 45% complete.

THE Santos-led GLNG project is now 45% complete and remains on track for first LNG in 2015.

Santos chief executive officer David Knox said construction on the Gladstone project was pleasing.

In Santos' fourth quarter report released on Thursday, Mr Knox said a significant milestone had been achieved for the GLNG underground gas transmission pipeline with the arrival of the last shipment of pipe in Queensland, and the start of pipeline burial.

All 420km of pipe for the gas transmission pipeline has been delivered to pipe yards in Gladstone and Port Alma.

A total of 108km of the mainland pipeline right-of-way has been cleared and graded, with 94km of pipe strung and 35km of pipe welded.

In December, pipeline burial in the Arcadia Valley began, which is the final step before rehabilitation works are carried out, the report said.

For the marine crossing, sealing of the access track started, and site pad and launch shaft preparation is continuing.

A tunnelling machine is being commissioned in Brisbane, and tunnel concrete segment moulds have been prepared. Segment fabrication began in early January.

On Curtis Island, construction of the two LNG trains and supporting infrastructure continues to progress.

Concrete wall lifts are underway for both LNG tanks, erection and welding of the temporary outer support brackets for the steel roof of LNG tank B has been completed and installation of roof plates has begun.

Sanctioned in January 2011, GLNG includes the development of CSG resources in the Bowen and Surat Basins in south-east Queensland, construction of a 420km underground gas transmission pipeline to Gladstone, and two LNG trains with a combined nameplate capacity of 7.8mtpa on Curtis Island.

The project has an estimated gross capital cost of US$18.5 billion from final investment decision to the end of 2015.

Topics:  curtis island, gladstone, glng, lng, mining, resources, santos




Join the Community.

Get your local news, your way.

Stay Connected

Update your news preferences and get the latest news delivered to your inbox.

Donations stolen from Eidsvold house fire family

TWO-year-old Austin Cotterill Remains in a critical condition following a house fire in Eidsvold on Tuesday.

Boy remains critical at Lady Cilteno Children's Hospital

Don’t forget about us: we deserve a better life

Bundaberg residents have the numbers stacked against them

Owners set to sell Mystery Craters

FOR SALE: Mystery Craters Leisure Park at South Kolan.

Lee Huxley and Ron Dodds are selling up.

Latest deals and offers

Surprise Gifts & Homeware

Ash Cumar, owner of Surprise Gifts & Homeware, has moved from Brisbane to open a shop in Bargara. Photo: Mike Knott / NewsMail

Ash Cumar, owner of Surprise Gifts & Homeware, has moved from Brisbane to open a...

Black Spot Funding - April 2016

BLACK SPOT: Member for Hinkler Keith Pitt will announce funding for improvements to several black spots on local roads in Bundaberg.
Photo: Max Fleet / NewsMail

Member for Hinkler Keith Pitt will announce funding for improvements to several...

RACQ releases SE Qld's worst choke points

Paul Turner, RACQ

Paul Turner from RACQ talks about our worst roads at peak time.

Demand for acreage lots pushes up property prices

Property values in Cooroy have increased 25%

Property values jump in Cooroy and Peachester.

How a sacked real estate agent made $725k in four months

Agent is now under investigation by the industry watchdog

RBA warns of future apartment oversupply

Toowoomba: Crest Apartments and Burke & Wills, Ruthven Street ( view from Neil Street) Photo Bev Lacey / The Chronicle

RBA says oversupply of apartments poses risk to household finances